Waterproofing of construction joints in the wall/floor junction

For retroactive waterproofing of the wall-floor junction the boreholes have to be drilled transecting the construction joint. The borehole should be drilled approximately into the middle of the construction joint.

In case of flowing water or when it is not certain if the crack is dry or wet KÖSTER 2 IN 1 is injected. It is injected twice 10 – 20 minutes apart to ensure that the joint is permanently and elastically sealed.

Always adhere to the specifications in the respective Technical Guidelines.

 

Back

Top
Austria Brasil Bulgaria China Croatia Denmark Finland Germany Ghana Greece Hungary Italy Japan Kazakhstan Korea Kuwait Latvia Lebanon Mexico Netherlands Norway Panama Philippines Poland Portugal Romania Russia Senegal Serbia Slovakia Slovenia South Africa Spain Thailand Turkey Ukraine United Kingdom United States of America